Project 2016 Intermediate

Lesson – Tracking Your Progress

Project 2016

Step-by-Step

Reschedule uncompleted work.

Switch to the Gantt Chart view and apply the Entry table. Select the 19 Frame Garage task and mark it as 50% complete. Drag the split bar to the left and scroll to view the task bar for the task.

The Carpenter has jury duty and probably cannot continue the rest of the work until after 9/4/18. You need to reschedule the remainder of the task.

Steps

Practice Data

1. To reschedule uncompleted work for specific tasks, select the tasks. The tasks are selected.

Click the 19 Frame Garage task, if necessary.

2. Select the Project tab.

Click

.

The Project ribbon appears.

3. From the Status group select Update Project . The Update Project dialog box appears. 4. Select the Reschedule uncompleted work to start after option. The option is selected.

Click

.

Click Reschedule uncompleted work to start after.

5. Type the desired date in the

Type 9/4/18.

Reschedule uncompleted work to start after field. The selected date appears in the field.

6. Select the Selected tasks option to reschedule work for selected tasks only. The option is selected.

Click

Selected tasks.

7. Select OK .

Click

.

The Update Project dialog box closes and uncompleted work before the selected date is rescheduled.