Lesson – Tracking Your Progress

18. Drag the split bar to the left to view the task bars in the right pane. 19. Mark 17 Electrical Adjust - Computer Room 50% complete. Reschedule the rest of the 17 Electrical Adjust - Computer Room task to start after 7/13/18, and select OK in the Project Wizard dialog box. Then, mark the job complete. 20. Apply a progress line using the status date and compare the data with the baseline plan. 21. Remove the progress line from the Gantt chart. 22. Enter an actual duration of 3.5 days for the 13 Lay Carpets in Board Room task. Enter an actual duration of .5 days for the 14 Install Board Room Furniture task. The task is done, so enter a remaining duration of 0 days and select Yes to assign the resources. Mark the 15 Board Room Complete task as 100% complete. 23. View the statistical summary information for the project. 24. Close the file without saving the changes.

OFFICEPRO, Inc.

Page 119

Made with FlippingBook - professional solution for displaying marketing and sales documents online