Project 2016 Intermediate

Lesson – Assigning Costs

Project 2016

If necessary, switch to the Resource Sheet view.

Steps

Practice Data

1. Select the Std. Rate field for the desired resource. The Std. Rate field is selected. 2. Enter the rate and, if applicable, include a forward slash (/) and the unit of time. The rate appears in the field.

Click the Std. Rate field for the 20 Backhoe resource.

Type 400/d.

3. Press [Enter] .

Press [Enter].

The standard rate and unit appear.

Notice that the 400/d appears as $400.00/day . The rate is formatted for currency, which is the default setting.

Practice the Concept: Complete the rate information for the following work resources. It is not necessary to type the currency symbol, decimal point, or decimals. In addition, you do not need to type the /hr since hours is the default standard unit.

ID

Resource Name

Std.Rate

16

Backhoe Operator

$25.00/hr

17

Superintendent

$35.00/hr

18

Phone Technician

$30.00/hr

19

Cable Specialist

$18.00/hr

Filter for Resources - Material and enter the rate information for the following resources:

Page 30