Lesson - Assigning Costs

ID

Resource Name

Material Label

Std.Rate

21

Tile

Square feet

$4.00

22

Concrete

yards

$80.00

23

Insulation

square feet

$2.00

24

Drywall

sheets

$8.00

Please check the cost of the project and see that it is now: $72,408.

A SSIGNING O VERTIME R ATES

Discussion

Enter an overtime rate for a work resource to calculate costs if overtime work is assigned to the resource. Overtime must be assigned to a task; it is not automatically calculated for work over 40 hours. If a resource is paid the same amount for both regular and overtime hours worked, enter the standard rate in the Ovt. Rate field, or the overtime hours are calculated at the zero-default rate. When you enter the overtime rate, enter the dollar amount followed by a forward slash (/) and the unit of time. The unit of time is only necessary if the rate is not hourly, which is the default.

Overtime rates only apply to work resources; therefore, this field is not available for material resources.

Procedures

1. Switch to the Resource Sheet view. 2. Select the Ovt. Rate field for the desired resource. 3. Enter the overtime rate and if applicable, include a forward slash (/) and the unit of time. 4. Press [Enter] .

Step-by-Step

Assign overtime rates.

If necessary, switch to the Resource Sheet view and remove any filters.