Lesson - Assigning Costs
$100.00 ($50 per use of the plumber resource x 2 plumbers). If the resource is only used for a minute or used for three days, the per-use cost is still applied.
For material resources, the per-use cost is only assigned once to a task where the material resource is used. The per-use cost, then, does not depend on the amount of the resource used. For example, there is a delivery charge of $50 for concrete. Concrete is used in two tasks; therefore, even if 100 yards of concrete are used, the per-use charge is only applied once to each task. The total per-use cost applied to the concrete resource is $100 ($50 per use x 2 tasks).
Procedures
1. Switch to the Resource Sheet view.
2. Select the View tab.
3. Select Details to use the Split screen .
4. Select the resource in the top pane to which you want to assign a per-use cost.
5. Select the value in the Per use field in the bottom pane.
6. Enter the cost per use of the resource.
7. Select
.
Step-by-Step
Assign a cost per-use to a resource.
If necessary, switch to the Resource Sheet view.
Split the window to display a combination view.