Lesson – Assigning Costs
Project 2016
Steps
Practice Data
1. Select the Ovt. Rate field for the desired resource.
For the 16 Backhoe Operator resource click the Ovt. Rate field
The Ovt. Rate field for the resource is selected.
2. Enter the overtime rate and, if
Type 37.5
applicable, include a forward slash (/) and the unit of time. The rate appears in the Ovt. Rate field.
3. Press [Enter] .
Press [Enter]
The overtime rate and unit appear in the Ovt. Rate field for the selected resource.
Practice the Concept: Assign the following overtime rates to the work resources listed:
ID
Resource Name
Ovt. Rate
17
Superintendent
35.00/hr
18
Phone Technician
45.00/hr
19
Cable Specialist
27.00/hr
A SSIGNING A P ER -U SE C OST TO A R ESOURCE
Discussion
Assign a per-use cost to both work resources and material resources. However, the per-use cost is calculated differently for each resource type. The per-use cost is added to the sum of the other resource charges, such as standard rate and fixed resource costs, for a resource cost total.
For work resources, the per-use cost is added one time for each unit of a work resource assigned to any task. For example, assign a per-use cost of $50 to the Plumber resource. If two plumbers are assigned to a task, the total per-use cost is