Project 2016 Intermediate
Project 2016
Lesson - Assigning Costs
Steps
Practice Data
1. Select the resource you want in the top pane. The resource is selected e. 2. In the bottom pane, select the Code field An insertion point appears in the Code field.
Click the 16 Backhoe Operator resource.
Click in the Code field.
3. Enter the code for the resource. The code appears.
Type POM880.
Practice the Concept: Assign the following codes to the remaining resources:
ID
Resource Name
Code
17
Superintendent
M654321
18
Phone Technician
PO7788
19
Cable Specialist
PO7900
23
Insulation
POM573
24
Drywall
POM300
25
Fees
COM100
26
Permits
COM101
C REATING A R ESOURCE R ATE T ABLE
Discussion
You may have resources with varying rates for different tasks or that require increases or decreases in their rates at certain points. Create resource rate tables to handle varying resource rates for both work resources and material resources.
Create up to five different cost rate tables containing up to 25 different sets of rates. In each table, enter initial rate information as well as rates effective on a certain date. You can also enter a percentage to represent an increase or decrease in the rate and Microsoft Project will calculate the new rate. Once the rate tables are created, assign rates to different tasks. To vary the resource rate for all tasks by date, you need to enter the dates and rates in the default rate table, which is table A.