Project 2016 Intermediate
Lesson – Assigning Costs
Project 2016
Creating a resource rate table
Procedures
1. Switch to the Resource Sheet view.
2. Double-click the resource for which you want to create a resource rate table.
3. Select the Costs tab.
4. Select the B , C , D , or E tab to create a new rate table, if desired.
5. Select the Effective Date field, if applicable.
6. Enter the date for which the rates in the new rate table are effective, if
applicable.
7. Select the desired rate field.
8. Enter the desired value in the selected field.
9. Continue to enter values in the rate fields as desired.
10. Select
.
Page 38