Project 2016 Intermediate
Project 2016
Lesson - Assigning Costs
Step-by-Step
Create a resource rate table.
If necessary, switch to the Resource Sheet view.
Steps
Practice Data
1. Double-click the resource for which you want to create a resource rate table. The Resource Information dialog box appears.
Double-click the 1 Laborer resource.
2. Select the Costs tab.
Click
.
The Costs page appears.
3. Select the B , C , D , or E tab to create a new rate table, if desired. The page appears with the Standard Rate field highlighted.
Click
.
4. Select the desired rate field . The desired field is selected.
Click the Standard Rate field in the first row.
5. Enter the desired value in the selected field. The desired value. 6. Select the next rate field where you want to add a value. The field is selected. 7. Enter the value in the selected field. The value appears in the selected field.
Type 30.
Click the Overtime Rate field.
Type 45
8. Select OK .
Click
The Resource Information dialog box closes and the cost rate table is created.