Lesson - Assigning Costs
Procedures
1. Switch to the Gantt Chart view.
2. Split the window.
3. Apply the Resource Cost format to the bottom pane.
4. Select the task in the top pane to which you want to assign a fixed resource cost.
5. Click in the Resource Name field in the bottom pane.
6. Select the Resource Name list.
7. Select the desired material resource assigned a fixed cost.
8. Select
.
Step-by-Step
Assign fixed material resource costs.
Switch to the Resource Sheet view and scroll to the bottom of the resource list. Notice that there are five material resources without material labels and with significant amounts in the Std. Rate field. Also notice that all five resources belong to the Fixed Cost group.
Switch to the Gantt Chart view. Split the window to display the Task Form view in the bottom pane. Activate the bottom pane and click the Format tab. Click the Cost icon in the Details group.
Steps
Practice Data
1. Select the task in the top pane to which you want to assign a fixed resource cost. The task is selected.
Click 19 Install Roof task in the top pane.