Project 2016 Intermediate
Project 2016
Lesson – Working with the Critical Path
12. Select
.
Step-by-Step
Assign overtime to a task.
Switch to the Gantt Chart view. Split the view to display the Task Form view in the bottom pane.
Steps
Practice Data
1. Select the task in the top pane
Click the 21 Install Windows task.
associated with the resource to which you want to assign overtime. The desired task is selected.
2. Select the bottom pane.
Click anywhere in the bottom pane.
The bottom pane is selected.
3. Select the Task Form Tools Format tab. The Format ribbon appears. 4. In the Details group select the Work command. The bottom pane changes to the Resource Work format.
Click Format.
Click
.
5. Select the Ovt. Work field in the
For the Laborer resource
bottom pane for the desired resource. The Ovt. Work field is selected.
click the
field
6. Enter the number of overtime hours. The number of overtime hours are entered.
Type 8.
7. Select OK .
Click
.
Overtime is assigned to the selected resources.
Notice that the duration of the 21 Install Windows task changed from 4 days to 3.5 days. Remove the split.