Project 2016 Intermediate
Lesson – Working with Baselines
Project 2016
Select task 8 Obtain Permits.
Steps
Practice Data
1. Click the Project tab
The Project ribbon appears
Click
.
2. Click the Set Baseline button.
The Set Baseline submenu appears.
Click
.
3. Choose the Set Baseline... from the submenu. The Set Baseline dialog box appears.
Click
4. Select the For: Select Tasks
Click
.
The Selected tasks option is selected.
5. Click the OK button.
Click
.
The current project baseline is updated.
7. Click Yes to overwrite the old baseline.
Click
.
The previous baseline is overwritten.
Notice that the Baseline field for the 8 Obtain Permits task changed to $1,480.00 and the Variance field changed to $0.00 . The variance for the 2 Conduct Site Survey task remains at $70.00 since this task was not added to the baseline.
Practice the Concept: Select task 2 Conduct Site Survey , use the Set Baseline dialog box to save the selected task to the baseline.
S AVING A DDITIONAL B ASELINES
Discussion
If you are creating a large project plan with many phases, you may want to save a separate baseline as you create or finish each phase of the plan. Microsoft Project can create up to 11 baselines for a project. The first baseline saved is named Baseline . Additional baselines are saved with the names Baseline 1-10 . Each baseline saves the task, resource, and assignment information for the project. Baseline is the baseline that appears on the Gantt Chart .
Page 78