Project 2016 Intermediate
Project 2016
Lesson – Working with Baselines
In addition to saving the duration of each task, baselines also save the start date, finish date, and all work and cost information for all tasks and assignments. Baselines also save resource information, which includes all work and cost data.
Update additional baselines the same way you update the main baseline. Save the entire project to an additional baseline or just selected tasks.
Procedures
1. Click
on the Project tab.
2. Select
from the drop-down menu.
3. Click the drop-down arrow for the Set Baseline list and choose a Baseline.
4. Choose if this is for the entire project or selected tasks.
5. Click
.
Step-by-Step
Save an additional baseline.
Steps
Practice Data
1. On the Project tab click the Set Baseline button.
The Set Baseline submenu appears.
Click
.
2. Choose Set Baseline... from the drop- down menu. The Set Baseline dialog box appears.
Click
.
3. Select a baseline from the Set Baseline drop-down list.
Click Baseline 1 , if necessary.
The options for a new baseline appear.
4. Select the Entire Project or Selected Tasks option. The desired option is selected.