Lesson – Working with Baselines
Viewing interim plan data
Procedures
1. Switch to the Gantt Chart view.
2. Select the Project tab.
3. Click the
button.
4. Select the
command.
5. Select the Save interim plan option.
6. Select the Copy list.
7. Select the fields you want to copy.
8. Select the Into list.
9. Select the fields where you want to copy the selected fields.
10. Select the Entire project option.
11. Select
.