Project 2016 Intermediate
Lesson – Working with Baselines
Project 2016
Step-by-Step
Save a project interim plan.
If necessary, switch to the Gantt Chart view.
Apply the Variance table to the view and drag the split bar as far right as possible. Constrain the 3 Develop Blueprints task so that it starts no earlier than 6/18/18 . Notice that there is now a variance for all the tasks affected by the change.
Steps
Practice Data
1. Select the Project tab.
The Project ribbon appears.
Click
.
2. Click the Set Baseline button.
The Set Baseline drop-down appears.
Select
.
3. Choose the Set Baseline... from the submenu. The Set Baseline dialog box appears. 4. Select the Set interim plan option. The Set interim plan option is selected.
Click
.
Click
.
5. Select the Copy list.
Click Copy .
A list of options appears.
6. Select the fields you want to copy. The fields appear in the Copy field.
Click Scheduled Start/Finish.
7. Select the Into list.
Click Into .
A list of options appears.
8. Select the fields where you want to copy the selected fields. The destination fields appear in the Into field.
Click Start1/Finish1.
9. Select the Entire project option.
Click
, if
The Entire project option is selected.
necessary.