Project 2016 Intermediate
Lesson – Working with Baselines
Project 2016
4. Point to the
button.
5. Select the
command.
6. Select the Clear baseline plan or Clear interim plan option.
7. Select the list for the selected plan.
8. Select the plan you want to clear.
9. Select the Entire project or Selected tasks option.
10. Select
.
Step-by-Step
Clear a baseline.
If necessary, switch to the Gantt Chart view, apply the Variance table, and drag the split bar as far right as possible.
Steps
Practice Data
1. Select the task for which you want to clear the baseline. The task is selected.
Click the 3 Develop Blueprints task.
2. Select the Project tab.
The Project ribbon appears.
Click
.
3. Point to the Set Baseline command. The Set Baseline drop-down appears.
Click
.
4. Choose Clear Baseline... from the submenu. The Clear Baseline dialog box opens. 5. Select the Clear baseline plan or Clear interim plan option. The plan is selected. 6. Select the list for the selected plan. A list of plans appears.
Click
.
Click
.
Click Clear interim plan .