Lesson – Working with Baselines
Steps
Practice Data
7. Select the plan you want to clear. The plan is selected. 8. Select the Entire project or Selected tasks option. The option is selected.
Click Start1/Finish1.
Click
.
9. Select OK .
Click
.
The Clear Baseline dialog box closes and the baseline information is cleared.
Notice that NA now appears in the Start1 and Finish1 fields for the 3 Develop Blueprints task. Select the 3 Develop Blueprints task, if necessary, and open the Set Baseline dialog box. Restore the date information by saving the Start1/Finish1 interim plan for the selected task. Then, hide the Start1 and Finish1 columns.
Close HOUSE14.MPP .