Lesson 4 – Working with Resources
ID
Task
Material Resource
Units
30
Insulation
Insulation
3000 square feet
31
Drywall
Drywall
170 sheets
33
Flooring
Tile
350 square feet
40
Cement Work
Concrete
15 yards
Close the Assign Resources dialog box.
A SSIGNING A C OST R ESOURCE TO A T ASK
Discussion
You can assign cost resources to tasks at the same time you assign work resources and material resources to tasks. As with material resources, cost resources do not perform work and do not typically impact the schedule, you can also wait and assign them when you begin to enter cost information.
When you assign a cost resource to a task, you need to enter the cost of the resource required for the task.
You assign cost resources in the Assign Resources dialog box, just as you assign work resources. In the cost field, you enter the amount of the resource needed for the task. If you have a cost resource called Airline fares, you simply enter the amount, such as 1200 for $1200 cost of the airline ticket.
Procedures
1. Switch to the Gantt Chart view.
2. Click the Assign Resources button on the Resource tab. 3. Select the task in the task list to which you want to assign a cost resource. 4. In the Assign Resources dialog box, select the corresponding field in the Cost column for the material resource you want to assign to the selected task. 5. Enter the desired value in the Cost field. 6. Select Assign . 7. Select Close to close the Assign Resources dialog box.