Project 2013 Introduction

Project 2013

Lesson 4 – Working with Resources

7. Select Close .

Step-by-Step

Assign a work resource to a task.

Switch to the Gantt Chart view and click on the Task Name in the second row - Conduct Site Survey to view the task bar for the 2 Conduct Site Survey task.

Steps

Practice Data

1. Click the Resource tab.

Click

.

The Resource ribbon appears.

2. Click the Assign Resources button The Assign Resources dialog box appears.

Click

.

3. In the Assign Resources dialog box, select the corresponding field in the Units column for the work resource you want to assign to the selected task. The Units field for the appropriate work resource is selected and a spin box appears in the field. 4. Enter the desired value in the Units field. The desired value appears in the Units field. The resource is assigned, the assigned resource appears with a checkmark at the top of the resources list in the Assign Resources dialog box, and the resource name appears next to the task bar for the selected task. 5. Select Assign .

Scroll as necessary and click the Units field for the Surveyor resource.

Click

to 200%.

Click

.

If necessary, move the Assign Resources dialog box and view the Gantt chart to see that the resource name and units appear next to the bar for the Conduct Site Survey task. Close the Assign Resources dialog box.