Lesson 4 – Working with Resources
Using the Team Planning View
Procedures
1. Click the Team Planner button on the View group of the Resource ribbon. 2. Scroll to locate unassigned tasks on the bottom pane. 3. Scroll to view resources in the upper pane. 4. Drag the unassigned task to the appropriate resource.
Step-by-Step
Assign work resources to a task using the Team Planner .
Steps
Practice Data
1. Click the Team Planner button on the View group of the Resource ribbon. The Team Planner view is displayed.
Click
.
2. Scroll to the time period of the task. The desired time period is displayed.
Scroll to the week of Jul 24, ’16.