Project 2013 Intermediate
Project 2013
Lesson 6 – Tracking Your Progress
The Progress Lines dialog box
NOTE
You can display additional progress lines at various dates using the Progress Line Dates list on the Dates and Intervals page in the Progress Lines dialog box. To remove any additional progress lines you have created, open the Progress Lines dialog box and use the Delete button. You can double-click an existing progress line to open the Progress Lines dialog box.
Procedures
1. Switch to the Gantt view. 2. Select the Gantt Chart Tools tab. 3. Point to the Gridlines command in the Format group. 4. Select the Progress Lines command. 5. Select the Dates and Intervals tab. 6. Select the Display option. 7. Select the At project status date or At current date option. 8. Continue to select options as desired.
9. Select
.