NOTE To vary the resource rate for all tasks by date, you need to enter the dates and rates in the default rate table, which is table A.

Procedures

1. Switch to the Task Usage view.

2. Scroll to view the task to which you want to assign a different resource rate

table.

3. Double-click the desired resource under the task.

4. Select the General tab.

5. Select the Cost rate table list.

6. Select the letter representing the desired table.

7. Select

.

Step-by-Step

Assign a resource rate table.

Switch to the Task Usage view.

Steps

Practice Data

1. Scroll to view the task to which you want to assign a different resource rate table. The task appears in the view. 2. Double-click the desired resource under the task. The Assignment Information dialog box opens.

Scroll to view the 22 Install Siding task.

Double-click the Laborer resource under the Install Siding task.

3. Select the General tab.

Click

, if

The General page appears.

necessary.