Project 2013 Intermediate
Project 2013
Lesson 3 - Assigning Costs
which is the default value for material resources. It is important that you do not change the Units value or the costs will increase. If you need to make changes to a fixed cost, you do so in the Std. Rate field for the resource.
Since fixed cost material resources do not impact the schedule, the duration of the task does not change when you assign the resource. Likewise, if the duration changes, the resource cost for the task remains fixed. You can assign resources with fixed costs to tasks that have other resources assigned to them.
Assigning a fixed resource cost
Procedures
1. Switch to the Gantt Chart view.
2. Split the window.
3. Apply the Resource Cost format to the bottom pane.
4. Select the task in the top pane to which you want to assign a fixed resource cost.
5. Click in the Resource Name field in the bottom pane.
6. Select the Resource Name list.
7. Select the desired material resource assigned a fixed cost.
8. Select
.
Step-by-Step
Assign fixed material resource costs.