Project 2013 Intermediate
Lesson 3 – Assigning Costs
Project 2013
Assigning a fixed resource cost
Procedures
1. Switch to the Gantt Chart view.
2. Split the window.
3. Apply the Resource Cost format to the bottom pane.
4. Select the task in the top pane to which you want to assign a fixed resource cost.
5. Click in the Resource Name field in the bottom pane.
6. Select the Resource Name list.
7. Select
.
8. Assign a cost
9. Select
.
Step-by-Step
Assign fixed material resource costs.
Page 70